

Soil Engineering (SEGL) were appointed to undertake a ground investigation for the proposed sixteen turbine windfarm located at Ewe Hill, to the east of Lockerbie, Dumfries & Galloway. The investigation required an assessment of the nature and composition of the ground at each proposed wind turbine positon, as well along the proposed access roads, and at the three borrow pit locations, from which materials would be sourced, if found to be of suitable geotechnical quality.
The heavily forested nature of the site presented unusual access challenges. SEGL deployed specifically modified and specially sourced plant to accommodate the challenging conditions, including a track mounted rotary drill rig and a rotary drill rig mounted on a Hagglund (ATV – all terrain vehicle), as well as two 360° LGP (low ground pressure) tracked excavators to complete the trial pitting, access track improvement, and clearing of borehole locations. Additional ATV’s (Hagglunds) were also deployed to transport the ancillary drilling equipment (compressors, pumps etc) and provide support vehicles for the drilling and trial pitting crews.
The scope of works comprised:
Ewe Hill 16 Windfarm covers an extensive upland area of approximately 438 hectares, consisting of upland hills and managed forestry. The work area, remote from the main compound, had no drive-on access and was predominately covered by soft organic peat deposits. SEGL used drilling rigs that were specially mounted by the in house workshop onto LPG ATV’s, and working with our preferred suppliers SEGL ensured that the correct plant and equipment, appropriate to the site conditions was utilised throughout the works. The chosen plant coped exceptionally well with the ground conditions which allowed SEGL to complete the works to the satisfaction of the client in less than 6 weeks. SEGL’s experienced site management team also ensured the works were completed safety and efficiently in challenging conditions. The main works were completed on programme and within budget, with challenging logistical constraints and difficult site conditions encountered throughout.
When a specialist Trenchless & Civils Contractor realised they had water ingress issues in their Launch Pit, they turned to Soil Engineering for a rapid turnaround Ground Investigation Due to project sensitivities we can’t name their project or client, but when it became apparent that the original GI for Stockton Drilling’s Direct Pipe Launch Pit […]
Read more ➜Transport Scotland have awarded Soil Engineering the latest contract on the A9, with a focus on sustainable ground investigation as a key deliverable. In announcing the award of the £635,000 project to Soil Engineering, Cabinet Secretary for Transport, Fiona Hyslop MSP highlighted the need to provide sustainable ground investigation from an environmental and social perspective. […]
Read more ➜Since our last update, our new Sonic Rig has been through commissioning and familiarisation training, and been back on transport to get to its first project.It’s been delivering sonic solutions on a project in the Highlands of Scotland, supporting another of our projects to deliver high-quality data for a key client.We can’t tell you where […]
Read more ➜